August 29, 2024: The start of the 2-year statute of limitations in Sutz vs. Lowe’s et al

As depicted in these infographics (click to enlarge), the statute of limitations in Sutz vs Lowe’s et al began on August 29, 2024, and expired on August 31, 2026.  Below are the details.


Chronology

8/1/24: The date Lowe’s promised Mr. Sutz his flooring installation would be completed.

8/23/24: Lowes’ unlicensed, incompetent installer destroyed Mr. Sutz’s sub-floor, then fled the job site, never to return.

8/26/24: At 9:00am, a technician with Lowes’ primary subcontractor, Service Pros, visited Mr. Sutz’s home, took pictures of his destroyed sub-floor, and transmitted them to Lowes’ Executive Customer Relations Dept. (”ECRD”).

8/26/24: Lowes’ ECRD representative, “MONTA S.,” emailed Mr. Sutz and told him he’d be in contact with the following day (8/27/24).

8/27/24: Monta told Mr. Sutz, in a call recorded on both sides, that it is Lowes’ policy that:

(1) Lowe’s cannot continue with the job, because the estimator did not know that Mr. Sutz’s wood planks were glued to his sub-floor

(2) The best Lowe’s will do is refund Mr. Sutz’s money, provided he sign a release of claims

Mr. Sutz told Monta this is completely unacceptable, and demanded that he get a supervisor on this matter, and call him back by the end of the day. Monta said that he would get back to him the next day (8/28), or no later than Monday (9/2).

8/29/24: LOWE’S EXPRESSES ITS FINAL POSITION ON WHAT IT DID TO MR. SUTZ

4:44pm: Monta emailed Mr. Sutz stating he tried calling him, but was unable to reach him, and requested that he return the call. See this email here.  Before 5:00pm, Mr. Sutz called Monta back, who told him that Lowes’ final decision is:

(1) It is not responsible for its installer’s destruction of Mr. Sutz’s sub-floor
(2) It will not fix the damage to his sub-floor
(3) It will not pay anyone to fix this damage
(4) it will not refund Mr. Sutz’s money unless he signs a release of claims, which will prevent him from being able to sue Lowe’s

8/30/24, 5:51am: Barely 12 hours after Lowe’s officially walked away from the job that Mr. Sutz paid it to do, he was treated at a nearby Emergency Room, for what was diagnosed as heart palpitations. The physician’s notes state that Mr. Sutz reported being under “a great deal of stress” because of what “a contractor” was doing to him, after a flood in his home. See this medical report here.


To share/print this item: